The Final Phase at Fobbing

May 30, 2025

Great progress photos of the High Road, Fobbing site in collaboration with Bellway Homes and CHP.

Delivering 41 homes for Affordable Rent and 18 Shared Ownership units. (3 bed houses, 2 bed Houses, 2bed flats and 1 bed flats)

8 Shared Ownership units remain under construction in the last phase - expected to be complete in June and October 2025.  

As Employers Agent for the scheme, PSW are privilaged to be a part of a dedicated and supportive team working together to deliver a succesful project.

The design of the apartment blocks was revised to meet the latest Part L requirements (introduced to improve energy efficiency and reduce carbon emissions, aliging with the UK’s Future Homes Standard)

Key updates include;

• Jet floor Beam and block system

• Loft roll increased to 500mm

• PV added to all plots

• Window U-value and G-values uplifted

• All plots - dual zone controls and Google Nest 3rd Gen stats